Japan Funds Floating Wind Installation R&D: Seven MLIT Projects, and the Vessel Question
Japan’s MLIT picked seven R&D projects for floating wind installation methods, mapping which bottlenecks stay pre-commercial and the vessel gap left open.
Track project progress and the ports, vessels, factories and supply chains needed to deliver offshore wind in Japan.
Start with the promotion-zone project list and the conditions that determine whether projects advance.
Check the selected developers and any schedule revisions, project by project.
Follow the sites left by the Round 1 withdrawal as they head for re-tender.
Follow the promising and preparation zones that precede promotion-zone designation.
Examine multi-port construction and the supplier clusters built around operating projects.
Use project locations and status to find detailed project profiles.
Open the project map →Japan’s MLIT picked seven R&D projects for floating wind installation methods, mapping which bottlenecks stay pre-commercial and the vessel gap left open.
Noshiro, Mitane and Oga offshore wind, Akita: the Round 1 developer exited in August 2025. Re-tender, council and EIA status, tracked monthly.
Saikai Enoshima offshore wind (420MW, JPY 22.18/kWh): Sumitomo and TEPCO Renewable Power. COD planned for August 2029. Schedule and EIA status, tracked monthly.
Murakami Tainai offshore wind (690MW, JPY 3.0/kWh): Mitsui, RWE and Osaka Gas. Turbines changed to 46 x 15MW; COD under review.
Yuza offshore wind (450MW, JPY 3.0/kWh): Marubeni, Kansai Electric, BP, Tokyo Gas and Marutaka. COD planned for June 2030; draft EIA report published July 2026.
Oga Katagami Akita offshore wind (315MW, JPY 3.0/kWh): JERA, J-POWER, Tohoku Electric and ITOCHU. COD planned for June 2028. Schedule and EIA status.
Happo Noshiro offshore wind (375MW, JPY 3.0/kWh): ENEOS, Iberdrola and Tohoku Electric. Onshore works due January 2026 were postponed.
Tsugaru offshore wind (Aomori Japan Sea South, 615MW, JPY 3.0/kWh): JERA, GPI and Tohoku Electric. COD planned for June 2030. Schedule and EIA status.
Kujukuri, Chiba is a Promising Zone. Its first council met on 15 December 2025; Eurus Energy and TEPCO RP have filed EIA documents.
Isumi, Chiba was named a Promising Zone in 2021, with one council meeting in February 2022. Eight developers have filed EIA primary documents. Tracked monthly.