Kujukuri Offshore Wind: Promising Zone Council and EIA Status

Offshore Kujukuri in Chiba (off Kujukuri, Sanmu and Yokoshibahikari) is a Promising Zone. The first statutory council met on 15 December 2025, starting formal talks toward designation. In the EIA, Eurus Energy’s procedure has reached the scoping document. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.

This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.

1. Where Kujukuri Stands (October 2026)

StatusPromising Zone
FoundationFixed-bottom expected
Council1st meeting held (15 December 2025)
EIAEurus Energy scoping document; TEPCO Renewable Power primary document
Next stepsCouncil talks and a consolidated opinion
Source: Agency for Natural Resources and Energy, MLIT, Ministry of the Environment and local government publications.

2. Toward Designation: Timeline

DateEventSource
Sep 2025Eurus Energy gives notice of its scoping documentMOE
15 Dec 20251st statutory council, the forum where national and local government, municipalities and fishers agree how the area is usedMETI

3. EIA Status: One Scoping and One Primary Document

Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. Two procedures cover Kujukuri: Eurus Energy has reached the scoping document, and TEPCO Renewable Power is at the primary document stage.

ProjectDeveloperStageNotice
Kujukuri offshore wind (provisional)Eurus Energy HoldingsScoping document2025/09
Kujukuri offshore wind (provisional)TEPCO Renewable PowerPrimary document2023/12
Source: Environmental Assessment Database (Ministry of the Environment), retrieved 31 October 2026.

4. Site Conditions

Water is mostly 20m to 30m deep, with some areas deeper than 30m. Several fishing ports lie nearby, and the nearest port is Naarai in Choshi.

For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.

What to Watch Next

  • The second and later council meetings, which will set the pace toward designation.
  • The council’s consolidated opinion. Once conditions on fisheries and local benefits are agreed, the zone can move to designation.
  • The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).