Offshore Kujukuri in Chiba (off Kujukuri, Sanmu and Yokoshibahikari) is a Promising Zone. The first statutory council met on 15 December 2025, starting formal talks toward designation. In the EIA, Eurus Energy’s procedure has reached the scoping document. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.
This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.
1. Where Kujukuri Stands (October 2026)
| Status | Promising Zone |
|---|---|
| Foundation | Fixed-bottom expected |
| Council | 1st meeting held (15 December 2025) |
| EIA | Eurus Energy scoping document; TEPCO Renewable Power primary document |
| Next steps | Council talks and a consolidated opinion |
2. Toward Designation: Timeline
| Date | Event | Source |
|---|---|---|
| Sep 2025 | Eurus Energy gives notice of its scoping document | MOE |
| 15 Dec 2025 | 1st statutory council, the forum where national and local government, municipalities and fishers agree how the area is used | METI |
3. EIA Status: One Scoping and One Primary Document
Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. Two procedures cover Kujukuri: Eurus Energy has reached the scoping document, and TEPCO Renewable Power is at the primary document stage.
| Project | Developer | Stage | Notice |
|---|---|---|---|
| Kujukuri offshore wind (provisional) | Eurus Energy Holdings | Scoping document | 2025/09 |
| Kujukuri offshore wind (provisional) | TEPCO Renewable Power | Primary document | 2023/12 |
4. Site Conditions
Water is mostly 20m to 30m deep, with some areas deeper than 30m. Several fishing ports lie nearby, and the nearest port is Naarai in Choshi.
For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.
What to Watch Next
- The second and later council meetings, which will set the pace toward designation.
- The council’s consolidated opinion. Once conditions on fisheries and local benefits are agreed, the zone can move to designation.
- The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).
Related DeepWind Articles
- Japan’s Offshore Wind Promising Zones
- Japan’s Offshore Wind Promotion Zones: A Complete Project List
Free reportWhich of April’s planning assumptions no longer hold? Our 17-page review of Japan’s offshore wind market, April to September 2026. Free when you subscribe to the Weekly. See what’s inside →