Project ExecutionPublished March 8, 2026Updated October 31, 2026

Happo Noshiro Offshore Wind (375MW): Developer, Schedule and Postponed Onshore Works

Offshore Happo Town and Noshiro City in Akita is a designated Promotion Zone under Japan’s Renewable Sea Area Act, the law that sets out how sea areas are allocated for offshore wind. Round 2 selected Happo Noshiro Offshore Wind GK (ENEOS Renewable Energy, Iberdrola, Tohoku Electric Power) for a 375MW fixed-bottom project. However, onshore works planned for January 2026 have been postponed, and a new schedule is under review, as the developer told the council in February 2026.

This page tracks where the project stands and what gets decided next, using primary sources. It is updated monthly.

1. Where Happo and Noshiro Stands (October 2026)

StatusPromotion Zone (designated 13 September 2021)
FoundationFixed-bottom
Tender roundSelected in Round 2 (March 2024)
DeveloperHappo Noshiro Offshore Wind GK (ENEOS Renewable Energy, Iberdrola Renewables Japan, Tohoku Electric Power)
Size and price375MW (25 × Vestas 15MW); JPY 3.0/kWh
ScheduleOnshore works (planned January 2026) postponed; new schedule under review. COD at selection: June 2029
Next stepsA revised construction schedule; the EIA final report
Source: Agency for Natural Resources and Energy, MLIT, Ministry of the Environment and local government publications. Schedules are the developer’s stated plans, not fixed dates.

2. From Designation to Construction: Timeline

DateEventSource
Sep 2021Designated as a Promotion ZoneMETI
Mar 2024Round 2 selects Happo Noshiro Offshore Wind GK at JPY 3.0/kWhMETI
Aug 2024Selected developer gives notice of its draft EIA reportMOE
25 Feb 20266th statutory council, the forum where national and local government, municipalities and fishers agree how the area is used. The developer explains that onshore works are postponed because the business environment has changedMETI

The developer says the new schedule, including the start of works, is under review, and that it intends to complete the project in line with its plan, taking account of the government’s measures for the business environment.

3. EIA Status: Selected Developer at Draft Report Stage

Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. The selected developer’s procedure has reached the draft report. A scoping document from JERA and J-POWER, which were not selected, also remains on record.

ProjectDeveloperStageNotice
Happo and Noshiro offshore wind (provisional)Happo Noshiro Offshore Wind GKDraft report2024/08
Happo and Noshiro offshore wind (provisional)JERA and J-POWERScoping document2023/04
Source: Environmental Assessment Database (Ministry of the Environment), retrieved 31 October 2026. 3 further procedure(s) in this area have been withdrawn.

4. Site Conditions

A site mostly under 30m deep, suited to fixed-bottom foundations. The developer plans to use Akita and Funakawa ports for foundations, Muroran Port for turbine installation, and Noshiro Port for operations and maintenance.

For a cost comparison with other zones on the same assumptions, see 👉 Cost Realities of Japan’s Offshore Wind: LCOE and IRR.

What to Watch Next

  • The new start date for onshore works. A later start would push back COD, set at June 2029 at selection.
  • What the government’s business-environment measures contain. The developer cites changed conditions, so measures such as price revisions will shape the schedule.
  • The EIA final report, the stage after the draft report that must be completed before construction.

Related DeepWind Articles

Free reportWhich of April’s planning assumptions no longer hold? Our 17-page review of Japan’s offshore wind market, April to September 2026. Free when you subscribe to the Weekly. See what’s inside →

Scroll to Top