Project ExecutionPublished March 7, 2026Updated October 31, 2026

Ishikari Offshore Wind: Promising Zone Council and 11 EIA Filings

Offshore Ishikari City in Hokkaido is a Promising Zone. The first statutory council met on 6 February 2026, starting formal talks toward designation. Eleven EIA primary documents have been filed, the most of any Promising Zone. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.

This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.

1. Where Ishikari Stands (October 2026)

StatusPromising Zone
FoundationFixed-bottom expected
Council1st meeting held (6 February 2026)
EIAEleven primary documents
Next stepsCouncil talks and a consolidated opinion
Source: Agency for Natural Resources and Energy, MLIT, Ministry of the Environment and local government publications.

2. Toward Designation: Timeline

DateEventSource
6 Feb 20261st statutory council, the forum where national and local government, municipalities and fishers agree how the area is used (Sapporo)Hokkaido Government

3. EIA Status: Eleven Primary Documents

Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. Eleven primary documents cover Ishikari, all at the first stage. The Ishikari Bay New Port wind farm, which operates inside the port area, is a separate project.

ProjectDeveloperStageNotice
Ishikari offshore wind (provisional)Sumitomo CorporationPrimary document2023/10
Ishikari offshore wind (provisional)Kansai Electric PowerPrimary document2023/02
Ishikari offshore wind (provisional)Ishikari Bay Offshore Wind GKPrimary document2022/04
Ishikari offshore wind (provisional)Japan Wind DevelopmentPrimary document2022/02
Ishikari offshore wind (provisional)MarubeniPrimary document2021/02
Ishikari offshore wind (provisional)Japan Renewable EnergyPrimary document2020/11
Ishikari offshore wind (provisional)Green Power InvestmentPrimary document2020/11
Ishikari offshore wind (provisional)JERAPrimary document2020/08
Ishikari offshore wind (provisional)CI Hokkaido GKPrimary document2020/07
Ishikari offshore wind (provisional)Ishikari Bay Offshore Wind GKPrimary document2020/07
Ishikari offshore wind (provisional)Cosmo Eco PowerPrimary document2019/08
Source: Environmental Assessment Database (Ministry of the Environment), retrieved 31 October 2026.

4. Site Conditions

The Promising Zone covers water 20m to 50m deep. Ishikari Bay New Port, close to the zone, is the expected port.

For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.

What to Watch Next

  • The second and later council meetings, which will set the pace toward designation.
  • The council’s consolidated opinion. Once conditions on fisheries and local benefits are agreed, the zone can move to designation.
  • The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).