Policy & RegulationPublished July 12, 2026Updated November 8, 2026

Japan’s GX Supply Chain Subsidy for Offshore Wind: 7 Factories Funded, 70% to Floating Foundations

Japan’s GX Supply Chain subsidy has now funded seven offshore wind factories across three rounds, with grants capped at JPY 18.5 billion in total. About 70% of that money went to three floating foundation yards in Nagasaki, Kitakyushu and Tsu. The factory size and 2030 deadline the program sets match the government’s 2040 pace, but they arrive years before domestic orders do.

Policy design→Execution reality→Bankability test
Key Takeaways
1. Seven awards in three rounds, and 70% to floating foundations
Five companies were selected in January 2025, JFE Engineering in January 2026 and Vestas Japan in July 2026. Of the JPY 18.46 billion in grant caps, JPY 13.03 billion (70.6%) went to three floating foundation yards. No blade or anchor factory has been funded yet.
2. The most money went where the required factory is smallest
Since 2025, each funded factory must reach a minimum annual output. Nacelles must reach 100 turbine sets a year; floating foundations only 20. Yet each foundation yard cost about JPY 13 billion to equip. The rules read as if Japan expects to build foundations at several yards in parallel.
3. Factories are due by FY2030; orders come later
A minimum-size nacelle plant equals 1.5 GW a year in 15 MW turbines, close to the annual pace of Japan’s 2040 floating target. GWEC’s forecast implies domestic installations of about 1 GW a year in the early 2030s, and floating orders at scale only from the mid-2030s. Vestas says its investment depends on market growth and its own orders.

👉 Background: Japan’s offshore wind policy framework

Who Got Funded: 7 Factories, January 2025 to July 2026

The GX Supply Chain Construction Support Program is a METI subsidy for factory investment in decarbonisation industries. It covers water electrolysers and perovskite solar cells as well as offshore wind, each in its own call. The offshore wind category is called “floating and other offshore wind power equipment”. Three calls in that category have produced these seven awards.

Announced Company (location) Product Grant cap (project cost)
2025-01-24 Toshiba Energy Systems & Solutions (Yokohama) Offshore wind nacelles JPY 2.26bn (6.78bn)
2025-01-24 Oshima Shipbuilding (Nagasaki) Floating foundations JPY 4.42bn (13.26bn)
2025-01-24 Narock (Wakayama, SME) Mooring lines JPY 0.84bn (1.68bn)
2025-01-24 Nippon Steel Engineering (Kitakyushu) Floating foundations JPY 4.27bn (12.80bn)
2025-01-24 Komai Haltec (Futtsu, Chiba) Tower parts JPY 1.01bn (3.04bn)
2026-01-28 JFE Engineering (Tsu, Mie) Floating foundations JPY 4.34bn (13.02bn)
2026-07-10 Vestas Japan (Wakamatsu, Kitakyushu) Final nacelle assembly JPY 1.33bn (2.65bn)
Source: adoption lists for the FY2024 second call (24 Jan 2025), FY2025 Project III (28 Jan 2026) and FY2025 supplementary Project I (10 Jul 2026), GX Supply Chain program secretariat. All amounts are caps; the lists note that actual grants may differ.

Together the seven projects cost about JPY 53.2 billion, and the grant caps add up to JPY 18.46 billion. Both are the ceilings listed by the secretariat; actual payments may be lower.

The share of costs covered varies by company. Five large companies (Toshiba ESS, Oshima Shipbuilding, Nippon Steel Engineering, Komai Haltec and JFE Engineering) received exactly one third. Narock, the only SME, received one half. Vestas is the outlier: a large company at exactly 50%.

Since the FY2025 call, a large company can get 50% if METI judges the project “ambitious”. Two conditions apply: no commercial plant for that product may already exist in Japan, and the product must be internationally competitive. METI has not said whether Vestas qualified on these grounds.

Each call came with a budget: about JPY 143.8 billion for FY2025 and JPY 83.3 billion for the FY2025 supplementary budget. Both figures cover every sector in the program, perovskite solar included. The amount set aside for offshore wind is unpublished. So is the number of applicants, which means the reason only one company was selected in each 2026 round cannot be known from outside.

Three of the seven have described their plans publicly. JFE Engineering will build floating foundations end to end at its Tsu works, from modules to final assembly. It targets 24 or more units a year by 2030. Komai Haltec opened Japan’s first full-scale offshore wind tower plant at Futtsu on 13 April 2026. Vestas will move the final stage of nacelle assembly, now done overseas, to Japan. Assembly and testing will take place at pre-assembly ports, where components are put together before installation, supported by a tooling base in Kitakyushu.

👉 Japan’s First Offshore Wind Tower Factory, Akita Blade Failure, and a New Floating Wind R&D Program

Vestas attached a condition in the same release. The investment depends on the continued growth of Japan’s offshore wind market and on Vestas winning orders for domestic projects. Kitakyushu already hosts Hibikinada, Japan’s largest operating offshore wind farm at 220 MW. It is also home to REACH, a supplier cluster of about 50 companies (our analysis of REACH).

Why Did 70% of the Money Go to Floating Foundations?

Grouping the grant caps by product shows how uneven the spending is.

Product Awards (sites) Grant caps Minimum factory output
Floating foundations 3 (Nagasaki, Kitakyushu, Tsu) JPY 13.03bn (70.6%) 20 sets/year
Nacelles 2 (Yokohama, Kitakyushu) JPY 3.59bn (19.4%) 100 sets/year
Tower parts 1 (Futtsu) JPY 1.01bn (5.5%) 30 sets/year
Mooring lines 1 (Wakayama) JPY 0.84bn (4.5%) 30 sets/year
Blades, anchors None 0 100 and 30 sets/year
Grant caps summed across the three adoption lists (DeepWind). Minimum outputs are from Table 2 of the FY2025 and FY2025 supplementary guidelines and include existing capacity. We could not confirm whether the FY2024 call set the same minimums.

Floating foundations, the structures that hold a turbine afloat, took 70% of the grants. They also carry the lowest required output per factory: 20 sets a year, a fifth of what a nacelle or blade plant must reach. The product with the most public money is the one where each factory is asked to make the least.

The way foundations are built explains much of this. Each one is a large steel structure that carries a whole turbine, and it needs a lot of assembly space. The three foundation yards cost JPY 12.8 to 13.3 billion each, around five times Vestas’s final assembly line. In DeepWind’s reading, METI set a small minimum per yard and spread the money across several, because one site cannot easily reach high volumes.

The arithmetic supports that reading. Building 1.5 GW of floating wind a year with 15 MW turbines needs 100 foundations a year, or five yards at the minimum size. Only JFE has published a figure (24 a year or more). Oshima Shipbuilding and Nippon Steel Engineering have not disclosed capacity or start dates, so how much Japan can actually produce depends on their plans and on future rounds.

The other gap is blades and anchors. Both are eligible, and neither has won an award in three rounds. The FY2025 supplementary call added six components (bearings, generators, gearboxes, control systems, power converters and hubs), and it produced a single award, to Vestas. Where turbine localisation stalls is covered in our analysis of Japan’s floating wind scale-up gap.

How the Program Works: One-Third Grants, Tied to Factory Size and a Deadline

The subsidy pays for equipment, buildings and systems in plants that make finished products. Projects that make only one part of a product are excluded, with one exception: raw and intermediate materials for blades. Large companies get up to one third of costs and SMEs up to one half. Projects judged “ambitious” can get one half and two thirds respectively.

Since the FY2025 call, funded companies take on four obligations:

  • Reach the minimum annual output for their product (Table 2) by FY2030, counting existing capacity
  • Keep producing for at least five years after the project ends
  • Report for five years how much output goes to offshore wind and how much elsewhere
  • Publish an ambitious 2030 capacity target aimed at world-leading scale

Table 2 states minimums in turbine sets per year. Converted to capacity with a 15 MW turbine (and 20 MW for reference), they look like this:

Product Minimum output At 15 MW At 20 MW
Nacelles, blades (plus six turbine components from the FY2025 supplementary call) 100 sets/year 1.5 GW/year 2.0 GW/year
Towers 30 sets/year 0.45 GW/year 0.6 GW/year
Mooring lines and chains, anchors 30 sets/year 0.45 GW/year 0.6 GW/year
Floating foundations 20 sets/year 0.3 GW/year 0.4 GW/year
Source: Table 2 of the FY2025 Project III and FY2025 supplementary Project I application guidelines. Conversion by DeepWind; turbine sizes are assumptions. Minimums apply to each funded factory and are separate from any national capacity plan.

The application guidelines and forms are published (in Japanese) on the GX Supply Chain secretariat’s offshore wind page.

Does 1.5 GW a Year of Factory Capacity Meet 2030 Demand?

Where it fits: the 2040 target’s annual pace

Japan aims to auction 10 GW of offshore wind by 2030 and 30 to 45 GW by 2040. At least 15 GW of the 2040 figure is floating. These are auction targets, and they do not guarantee installed capacity. Commercial floating auctions are planned from FY2029. Spread over the roughly 11 years to 2040, 15 GW comes to about 1.4 GW a year. One minimum-size nacelle plant implies 1.5 GW. In DeepWind’s reading, Table 2 fixes in advance the factory size that the target would need if it ran on schedule.

Where it is early: FY2030 comes before the orders

Demand to fill that capacity will not exist in Japan by FY2030. The Global Wind Energy Council (GWEC) forecasts 3.5 GW installed in Japan by 2030 and 8.4 GW by 2035. That is about 1 GW a year in the early 2030s. Even worldwide, GWEC expects only 423 MW of new floating wind in 2030. Auctions, developer selection, FID (final investment decision) and component orders take several years. Floating component orders are unlikely to arrive at scale before the mid-2030s (GWEC’s 3.5 GW forecast and the FID barrier).

Who Fills the Gap? Fixed-Bottom Projects and Exports

The category’s full name covers floating “and other” offshore wind equipment. Nacelles, blades and towers serve fixed-bottom projects too, where the foundation stands on the seabed. Until floating demand arrives, factories finished by FY2030 will rely on fixed-bottom work. That means Rounds 2 (about 1.8 GW) and 3 (about 1.05 GW), now in construction, plus re-tenders and future auctions.

Exports are the other outlet. The guidelines require five years of reporting on how much output goes to offshore wind, and METI may attach conditions if that share is low. They also require a world-leading capacity target. In DeepWind’s reading, METI does not expect domestic offshore wind orders alone to fill these plants in the early 2030s, and is counting on export production as well. For the wider industrial policy, see Japan’s offshore wind industrial strategy; for the auction targets, see Japan’s 10 GW and 45 GW goals.

Bankability Note

The grant covers one third to one half of a large company’s investment, but the plant’s fixed costs remain. Whether the factory pays back depends on utilisation, and utilisation depends on orders. For a developer that plans to buy components locally, supply security depends on how much other work that supplier’s plant has. Lenders assessing supply security may need to ask what work is expected to fill a supplier’s plant. Mechanisms that stabilise project revenue, such as the Long-Term Decarbonization Auction (LTDA), also support supplier investment indirectly.

DeepWind View

Subsidies build the factories; auction volume and timing will decide whether they run.

The hardest part of floating wind manufacturing is the foundation, a heavy steel structure. The program puts its money there and spreads production across several yards. As a design, that is coherent.

The timing is the problem. Several years separate the FY2030 deadline from the arrival of floating orders at scale. In that gap, suppliers carry the fixed costs, and fixed-bottom work and exports must keep the plants running. Vestas’s condition, that its investment depends on orders, reads as the market saying that a grant alone cannot carry that risk.

Three things to check next: how much volume future fixed-bottom auctions and the first commercial floating auctions put on the table, and how far ahead; what Oshima Shipbuilding and Nippon Steel Engineering plan to build; and whether any blade or anchor plant is funded.

Frequently Asked Questions

Q: What is Japan’s GX Supply Chain subsidy?
It is a METI program that pays part of the cost of factories for decarbonisation industries. For offshore wind, it funds plants that make finished nacelles, blades, towers, mooring lines, anchors and floating foundations. The FY2025 supplementary call added six turbine components, bringing the list to 12.

Q: What are the subsidy rates?
Large companies receive up to one third of costs and SMEs up to one half. Projects judged ambitious can receive one half and two thirds. The published budgets cover all sectors, so the offshore wind allocation is unknown.

Q: Which offshore wind companies have been selected?
Toshiba Energy Systems & Solutions, Oshima Shipbuilding, Narock, Nippon Steel Engineering and Komai Haltec in January 2025; JFE Engineering in January 2026; and Vestas Japan in July 2026. Their grant caps total JPY 18.46 billion.

Related DeepWind Articles

Free reportWhich of April’s planning assumptions no longer hold? Our 17-page review of Japan’s offshore wind market, April to September 2026. Free when you subscribe to the Weekly. See what’s inside →

Scroll to Top