Cost & Commercial ViabilityPublished November 17, 2026

Japan’s New State Loans for Power Plants: Market-Rate Interest, a 30% Cap, and an LTDA or PPA Gate for Offshore Wind

Japan will lend state money to power plants of 500 MW or more, under rules reported to a METI committee on 10 November 2026. Interest follows market rates, and the state share is capped at about 30% of total debt. For offshore wind, the loan adds tenor and volume. Access depends on showing revenue backed by the Long-Term Decarbonization Auction or a long-term PPA with an investment-grade buyer.

Policy design→Execution reality→Bankability test
Key Takeaways
1. The state loan adds tenor and volume, at market rates
The rate is set against corporate bond yields and bank lending terms. METI’s worked example gives 4.5%. One type of grid loan in the same scheme is priced at about 0.1%, so generation sits in a different bucket.
2. Banks still decide the other 70%
The state share is capped at about 30% of total project debt, and the application must include letters of intent from private lenders. A project that banks will not fund cannot get this loan on its own.
3. For offshore wind, the LTDA gate opens once and is narrow
Offshore wind won nothing in LTDA Round 3. Round 4 admits only zero-premium Round 2 and 3 projects, with a 500 MW cap on expected capacity. Later projects are expected to rely on long-term PPAs.

👉 Background: offshore wind cost structure

What did Japan’s amended Electricity Business Act create for power plants of 500 MW or more?

The amended Electricity Business Act passed on 17 July 2026. It lets the Minister of Economy, Trade and Industry certify development plans for large power plants and transmission lines. The Organization for Cross-regional Coordination of Transmission Operators (OCCTO), the body that coordinates supply, demand and grid planning across Japan, then lends to the certified projects.

The money comes from FILP, the Fiscal Investment and Loan Program. Under FILP, the state raises funds through its own bonds and lends them long term for policy goals. A METI working group set the terms for power plants at meetings on 28 July and 25 August. They were reported to the Subcommittee on the Next-Generation Electricity and Gas Business Foundation on 10 November.

Item Decided terms for power plants
Eligibility Output of 500 MW or more. Priority to decarbonized sources eligible for the LTDA
Cap About 30% of total project debt. Even in a single year, OCCTO does not supply all borrowing
Tenor May exceed typical private loan tenors, matched to the investment payback period
Interest Corporate bond yields as the main reference, with bank lending terms also considered
Repayment support Checks such as an LTDA award, or a long-term PPA with an investment-grade buyer
Application A funding plan covering OCCTO and private loans, plus letters of intent from private lenders
Source: METI, Subcommittee on the Next-Generation Electricity and Gas Business Foundation, 7th meeting, Document 5 (10 Nov 2026), pp. 14, 15, 26

The documents never mention offshore wind. Eligibility is set by output and by repayment support, so the analysis below applies those tests to offshore projects.

Why is the rate around 4.5% in METI’s example, when one grid loan type is about 0.1%?

FILP lending is meant to support private finance without undercutting it. So the rate is pegged to the market. The main reference is the yield on the borrower’s corporate bonds, adjusted with what banks actually charge.

METI gives one worked example. A 10-year bond yields 3.5%, and the OCCTO loan runs 25 years. To cover the gap in tenor, METI adds the spread between 25-year and 10-year government bonds, 3.9% minus 2.9%, or 1.0%. The result is 4.5%. METI says both the method and the figures are only an example.

For project finance, where lenders are repaid only from the project’s own cash flow, bond yields are hard to observe. The working group papers propose using the rate private banks offer on the same project. They also propose a floor equal to OCCTO’s own FILP funding cost plus operating expenses.

Grid lending works differently. For one category of regional transmission loans, funded by subsidies from interconnector congestion revenue, the assumed rate is about 0.1%. Power plants do not get that kind of money.

What helps, then, is tenor. Loans are repaid from each year’s revenue. For the same amount borrowed, a longer tenor means smaller annual payments and more headroom. Offshore wind assets run for decades and take years to pay back their capital cost. Borrowing longer than banks usually allow matters even at the same rate.

Who lends the other 70% under a 30% state cap?

Volume is the second lever. The cap applies to total project debt, not to each year’s needs. METI’s example is a 5-year build with ¥500 billion of debt, of which OCCTO lends ¥150 billion. In year one OCCTO provides half of the ¥100 billion drawn, and by year five its share falls to ¥10 billion. The cumulative share can go above 30% for a while, but must end at 30% or less.

That leaves about 70% to private banks. When applying, the developer must also submit a letter of intent (LOI) from private lenders. The state loan sits on top of a bank deal that already exists in outline.

Banks asked for this. In August 2025, Sumitomo Mitsui Banking Corporation told a METI working group that private lenders alone might not be able to fund the required amounts on good terms. In June 2024, the Development Bank of Japan said its energy loan book was already about the size of its equity capital. It added that other banks face similar limits on how much they lend to one sector.

The scheme fills that gap with a 30% top-up. If the shortfall is lending capacity, it works. If banks decline because the revenue case is weak, the 30% never arrives.

What counts as repayment support: an LTDA award or a long-term investment-grade PPA?

FILP is public money, so OCCTO must be confident of repayment. For power plants, it will check that investment recovery is predictable. METI gives two examples. One is an award in the Long-Term Decarbonization Auction (LTDA), which pays decarbonized plants a fixed capacity revenue for 20 years or more. The other is a long-term PPA, a power purchase agreement, with an investment-grade counterparty, meaning a credit rating of BBB- or higher.

The list ends with “etc.”, so other forms of support are not ruled out. The documents do not say how projects under FIP, Japan’s feed-in premium scheme, will be treated.

Offshore wind won nothing in LTDA Round 3, and Round 4 opens one narrow window

In LTDA Round 3, bid in fiscal 2025, decarbonized sources won 4.26 GW. None of it was offshore wind. Projects that receive FIT or FIP support are normally barred, to prevent double recovery of fixed costs.

Round 4 makes an exception. Projects selected in Round 2 and Round 3 of the offshore wind tenders may enter if they are zero-premium projects. That means their bid price asks for almost no top-up above market prices. To qualify, they must give up the part of their FIP payment that covers balancing costs, the cost of managing output swings.

The window has two limits. The first is volume. METI expects up to about 700 MW of offshore wind to enter, and capped offshore wind at 500 MW. Its offshore price ceiling, ¥340,000 to ¥700,000 per kW per year, is above the ¥200,000 benchmark that applies to most sources. METI cited the cost to electricity consumers.

The second is time. The measure applies only to Round 2 and 3 projects. METI does not expect projects from later tenders to join the LTDA at all.

Note that “500 MW” means two different things here. The loan threshold counts installed output. The LTDA cap counts expected capacity, which is output multiplied by an adjustment factor for how reliably a plant produces at times of tight supply. For offshore wind, expected capacity is well below installed output.

From Round 4 tenders onward, a long-term PPA is the gate

For offshore projects from Round 4 tenders onward, that leaves the long-term PPA with an investment-grade buyer. In a separate paper at the same meeting, METI described corporate PPAs from decarbonized sources as one way for generators to secure finance. A corporate PPA is a long-term contract in which a company buys power directly from a generator. Among the GX regional co-creation subsidy awards announced on 30 October, one plan uses a corporate PPA with new offshore wind.

The loan rules ask for an investment-grade counterparty and a long contract. They do not yet say how many buyers, for how long, or for what share of output, would satisfy that test.

Bankability Note

Lenders care less about profit than about whether debt service is ever missed. They test the hardest year, using the minimum DSCR, the ratio showing how comfortably cash flow covers debt service. A longer tenor lowers annual payments and lifts that ratio. It leaves the interest rate and the power price unchanged. DeepWind uses a minimum DSCR above 1.35x as its guide for financeable projects; this is a DeepWind setting. Japan Credit Rating Agency’s 2021 guide for wind project finance ratings cites about 1.5x for A and the low 1.3x range for BBB. Whether revenue rests on the LTDA or a PPA shapes how the banks funding the other 70% read the project.

The 500 MW line: two of the six Round 2 and 3 projects clear it

The threshold uses combined output. Several units at the same plant count together if the total reaches 500 MW. Unrelated projects cannot be bundled, and projects built far apart in time cannot be filed as one plan.

Japan’s Round 2 and Round 3 tenders selected six offshore wind projects, ranging from 315 MW to 684 MW. Two exceed 500 MW. The other four sit between 315 MW and 450 MW. Single offshore projects cluster right around the line.

The definition of a “large-scale generator” eligible to borrow is still to be set by a separate working group. The draft review criteria include project feasibility, covering construction readiness, supply chain and workforce. So the same review that checks the money also checks whether the project can be built.

Four things to watch: enforcement, definitions, LTDA Round 4, and the first loan

  • Enforcement and lending standards: METI aims to bring the law and its ordinances into force around December. The first test is how the lending standards set rates for project finance.
  • The “large-scale generator” definition: Watch how a project company created for a single offshore wind farm is treated.
  • LTDA Round 4 results: How much offshore wind bids into the 500 MW expected-capacity cap.
  • The first borrower: A draft schedule points to a first loan around March 2027. The type of plant certified first will show where the scheme is aimed.
DeepWind View

A state loan cannot turn a price problem into a funding problem.

This scheme makes funding easier for projects whose revenue is already secured. It lends for longer, and it adds up to 30% when bank balance sheets are full. Where the gap is debt volume and tenor, it helps. It cannot rescue a project whose revenue does not cover its costs, because the rate tracks the market and banks still decide on 70% first.

For offshore wind, the question has moved to how revenue is secured. Round 2 and 3 projects have one pass through LTDA Round 4. Later projects will need long-term PPAs. Two developments would change this reading. One is lending standards that treat project finance rates or tenors differently. The other is use of a flexible cap for very large project finance deals, which the Ministry of Finance’s FILP council said in December 2025 should be considered.

Related DeepWind Articles

Subscribe to DeepWind Weekly

DeepWind Weekly tracks Japan’s offshore wind market beyond headline announcements, focusing on execution risk, cost structure, project viability, supply-chain constraints, and policy implications.

Subscribe to receive weekly intelligence on Japan’s offshore wind market.

Free reportWhich of April’s planning assumptions no longer hold? Our 17-page review of Japan’s offshore wind market, April to September 2026. Free when you subscribe to the Weekly. See what’s inside →

Scroll to Top