Offshore Hibikinada in Fukuoka was newly listed as a Promising Zone on 3 October 2025 and, on the same day, selected for a JOGMEC site survey. No statutory council has met yet. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.
This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.
1. Where Hibikinada Stands (October 2026)
| Status | Promising Zone (newly listed 3 October 2025) |
|---|---|
| Foundation | Fixed-bottom expected |
| Council | Not yet convened |
| EIA | None found for this zone |
| Next steps | Start of the statutory council; JOGMEC survey |
2. Toward Designation: Timeline
| Date | Event | Source |
|---|---|---|
| 3 Oct 2025 | Listed as a Promising Zone and selected for a JOGMEC site survey | METI |
3. EIA Status: None Found
Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. No EIA procedure for this zone appears in the Ministry of the Environment database (as of 31 October 2026). The Kitakyushu Hibikinada wind farm inside the Kitakyushu port area is a separate project.
4. Site Conditions
A fixed-bottom candidate site facing the Hibiki Sea in northern Kyushu.
For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.
What to Watch Next
- Whether the statutory council convenes. No council has met yet, so the first meeting is the next milestone.
- Start of the JOGMEC survey, which depends on the government budget.
- The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).
Related DeepWind Articles
- Japan’s Offshore Wind Promising Zones
- Japan’s Offshore Wind Promotion Zones: A Complete Project List
Free reportWhich of April’s planning assumptions no longer hold? Our 17-page review of Japan’s offshore wind market, April to September 2026. Free when you subscribe to the Weekly. See what’s inside →