Project ExecutionPublished February 19, 2026Updated October 31, 2026

Shimamaki Offshore Wind: Promising Zone Status

Offshore Shimamaki in Hokkaido (fixed-bottom) is a Promising Zone. No statutory council has met yet. Five developers have filed EIA primary documents. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.

This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.

1. Where Shimamaki Stands (October 2026)

StatusPromising Zone (the floating area is a Preparation Zone)
FoundationFixed-bottom expected
CouncilNot yet convened
EIAFive primary documents
Next stepsStart of the statutory council
Source: Agency for Natural Resources and Energy, MLIT, Ministry of the Environment and local government publications.

2. Toward Designation: Timeline

DateEventSource
3 Oct 2025Confirmed as a Promising Zone in the government’s annual reviewMETI

3. EIA Status: Five Primary Documents

Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. Five primary documents cover Shimamaki, all at the first stage.

ProjectDeveloperStageNotice
Shimamaki offshore wind (provisional)Kansai Electric Power, RWE Renewables JapanPrimary document2025/01
Shimamaki offshore wind (provisional)Eurus Energy HoldingsPrimary document2024/07
Shimamaki offshore wind (provisional)Japan Wind EnergyPrimary document2022/10
Shimamaki offshore wind (provisional)Cosmo Eco PowerPrimary document2022/09
Shimamaki offshore wind (provisional)Hokkaido Offshore Wind Development GKPrimary document2022/03
Source: Environmental Assessment Database (Ministry of the Environment), retrieved 31 October 2026.

4. Site Conditions

A Sea of Japan site split into a fixed-bottom part (Promising Zone) and a floating part (Preparation Zone).

For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.

What to Watch Next

  • Whether the statutory council convenes. No council has met yet, so the first meeting is the next milestone.
  • The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).