Offshore Shimamaki in Hokkaido (fixed-bottom) is a Promising Zone. No statutory council has met yet. Five developers have filed EIA primary documents. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.
This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.
1. Where Shimamaki Stands (October 2026)
| Status | Promising Zone (the floating area is a Preparation Zone) |
|---|---|
| Foundation | Fixed-bottom expected |
| Council | Not yet convened |
| EIA | Five primary documents |
| Next steps | Start of the statutory council |
2. Toward Designation: Timeline
| Date | Event | Source |
|---|---|---|
| 3 Oct 2025 | Confirmed as a Promising Zone in the government’s annual review | METI |
3. EIA Status: Five Primary Documents
Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. Five primary documents cover Shimamaki, all at the first stage.
| Project | Developer | Stage | Notice |
|---|---|---|---|
| Shimamaki offshore wind (provisional) | Kansai Electric Power, RWE Renewables Japan | Primary document | 2025/01 |
| Shimamaki offshore wind (provisional) | Eurus Energy Holdings | Primary document | 2024/07 |
| Shimamaki offshore wind (provisional) | Japan Wind Energy | Primary document | 2022/10 |
| Shimamaki offshore wind (provisional) | Cosmo Eco Power | Primary document | 2022/09 |
| Shimamaki offshore wind (provisional) | Hokkaido Offshore Wind Development GK | Primary document | 2022/03 |
4. Site Conditions
A Sea of Japan site split into a fixed-bottom part (Promising Zone) and a floating part (Preparation Zone).
For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.
What to Watch Next
- Whether the statutory council convenes. No council has met yet, so the first meeting is the next milestone.
- The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).
Related DeepWind Articles
- Japan’s Offshore Wind Promising Zones
- Japan’s Offshore Wind Promotion Zones: A Complete Project List