Aomori Offshore (Japan Sea, north) is a Promising Zone. No statutory council has met yet. The southern zone already has a Round 3 developer, while the north awaits its next step. A Promising Zone is a candidate for designation that the government discusses in detail through a statutory council. Once the council agrees its opinion, the zone can move to Promotion Zone designation.
This page tracks where the zone stands in the process and what gets decided next, using primary sources. It is updated monthly.
1. Where Aomori Japan Sea North Stands (October 2026)
| Status | Promising Zone |
|---|---|
| Foundation | Fixed-bottom expected |
| Council | Not yet convened |
| EIA | One scoping document from 2018 remains |
| Next steps | Start of the statutory council |
2. Toward Designation: Timeline
| Date | Event | Source |
|---|---|---|
| 3 Oct 2025 | Confirmed as a Promising Zone in the government’s annual review | METI |
3. EIA Status: One Older Scoping Document
Japan’s environmental impact assessment runs in four stages: a primary document, a scoping document, a draft report with survey and prediction results, and a final report. The only procedure on record for the north is a 2018 scoping document from Aomori Seihoku-oki Offshore Wind GK.
| Project | Developer | Stage | Notice |
|---|---|---|---|
| Aomori Japan Sea North offshore wind (provisional) | Aomori Seihoku-oki Offshore Wind GK | Scoping document | 2018/08 |
4. Site Conditions
A fixed-bottom candidate site on the Sea of Japan, next to the southern zone off Tsugaru City.
For a cost comparison with other zones on the same assumptions, see 👉 Promising Offshore Wind Zones in Japan: LCOE and IRR.
What to Watch Next
- Whether the statutory council convenes. No council has met yet, so the first meeting is the next milestone.
- The annual zone review. The government reviews and publishes Promotion, Promising and Preparation Zones each year (last on 3 October 2025).
Related DeepWind Articles
- Japan’s Offshore Wind Promising Zones
- Japan’s Offshore Wind Promotion Zones: A Complete Project List
Free reportWhich of April’s planning assumptions no longer hold? Our 17-page review of Japan’s offshore wind market, April to September 2026. Free when you subscribe to the Weekly. See what’s inside →