Introduction
One of the most critical factors in commercializing floating offshore wind is controlling cost structure. Investors and developers need clarity on how large-scale deployments and technological advancements can lower LCOE (Levelized Cost of Electricity). This article breaks down CAPEX and OPEX line items in detail and presents an LCOE case study to reveal the economic reality of floating systems.
CAPEX Breakdown
Initial capital expenditure (CAPEX) for floating offshore wind is the largest single investment component. It can be divided into five major categories, each of which varies significantly with project scale and site conditions:
- Turbine Unit Cost
• Manufacturing: 15 MW+ turbines require high-strength composites and precision machining; typical cost ranges from €1.0 – 1.5 million per MW. Advanced materials (carbon fiber blades, high-torque generators) and efficiency upgrades push costs upward.
• Transport & Pre-installation: Sea transport to port, dry-dock assembly, crane lifts, and quality testing add roughly 5 – 10 % of turbine manufacturing cost. - Platform Fabrication & Transport
• Hull Fabrication: Semi-submersible, SPAR, barge, or TLP hulls require large-scale steel welding and specialized assembly; module costs typically run €0.8 – 1.2 million per MW, depending on design reuse and mass-production level.
• Port Assembly & Towage: Completed hulls are towed to site by tug over 100 – 300 km; towage costs about €200 – 300k per operation, translating to €0.1 – 0.2 million per MW once insurance and attachments are included. - Installation & Mooring Works
• Vessel Charter: Self-Elevating Platforms (SEP) or DP vessels cost €200 – 300k per day. A typical installation of one unit takes 10 – 15 days, yielding €2.0 – 4.5 million per MW.
• Mooring & Anchor Installation: Catenary or tension-leg anchor installation, seabed surveys, and dedicated installation vessels cost about €0.2 – 0.4 million per MW. - Grid Connection Infrastructure
• Subsea Cables: AC or DC cables cost €0.3 – 0.5 million per km. For distances over 20 km, HVDC converters (€1.5 – 2.5 million per converter) become cost-effective.
• Onshore Substation & Grid Tie-in: Cable landings, substation construction, and grid interconnection add €0.1 – 0.2 million per MW, including environmental assessments and local consultations. - Engineering, Certification & EIA
• Engineering & Design: Detailed platform, mooring, and grid integration studies amount to 3 – 5 % of total CAPEX (~€0.1 – 0.15 million per MW).
• Certification Fees: DNV, ClassNK, and others charge for design reviews, FAT, and SAT—approximately €20 – 50k per MW (~€0.02 – 0.05 million per MW).
• Environmental Impact Assessment (EIA): Marine biology, noise, visual, and cultural heritage surveys cost roughly €0.03 – 0.1 million per MW.
Estimated Total CAPEX: ~€3.4 million per MW
OPEX Breakdown
Operating expenditure (OPEX) occurs annually once the farm is operational. Key cost elements include:
- Scheduled Maintenance
• Drone & ROV Inspections: Unmanned aerial and underwater inspections cost €100 – 200k per mission.
• Crew & Vessel Charter: Technicians and crew aboard maintenance vessels (20–30 days/year at €20 – 30k/day) total ~€0.08–0.12 million per MW per year. - Component Replacement & Emergency Repairs
• Major Component Swaps: Gearboxes, generators, bearings, and blades replaced based on MTBF; ~€0.03–0.05 million per MW per year.
• Subsea Cable Repairs: Anchor impacts or wear may require €0.1 million+ per event, with costs spread via insurance or pooled risk funds. - Operations Management & Monitoring
• SCADA & Analytics: 24/7 remote monitoring, data analytics, and staff support €0.02–0.04 million per MW.
• Predictive Maintenance Software: AI-driven vibration and temperature monitoring licenses near €0.01 million per MW. - Offshore Access Costs
• Vessel fuel, maintenance, and standby time for weather delays add €0.02–0.03 million per MW per year.
• Contingency for weather downtime typically 5–10 % of OPEX budget. - Insurance & Risk Financing
• Property damage & business interruption insurance costs €0.03–0.06 million per MW per year.
• FX, political, and supply chain hedges add ~€0.01 million per MW.
Estimated Total OPEX: ~€0.25–0.30 million per MW per year
LCOE Case Study
This case study considers a 200 MW semi-submersible project in 60 m water depth. Assuming a WACC of 6.5 %, a 25-year operational lifetime, and a capacity factor of 32.5 %, the LCOE is calculated as follows:
Item | Cost (M€/MW) | Details |
---|---|---|
Turbine Unit | 1.2 | Manufacturing & transport |
Platform Hull | 1.0 | Fabrication, assembly & towage |
Installation & Mooring | 0.5 | SEP vessel & mooring works |
Grid Infrastructure | 0.3 | Subsea cable & substation |
Engineering & Certification | 0.1 | Design & EIA |
Total CAPEX | 3.1 | |
Annual OPEX | 0.13 | 25-year average |
LCOE | €135/MWh | (~¥18/kWh) |
Cost Reduction Strategies
To enhance the economic competitiveness of floating offshore wind, deploy a multi-faceted cost reduction program:
- Pursue Economies of Scale
• Scale project size from 100 MW to 500 MW and 1 GW to leverage bulk procurement, standardized construction methods, and optimized installation campaigns; potential CAPEX reduction of 10–15 % at ≥1 GW scale. - Drive Technological Innovation & Standardization
• Adopt modular platform designs to reduce engineering and verification cycles.
• Explore next-gen structures: hybrid steel-concrete SPARs, vertical-axis turbines, and advanced lightweight materials to cut steel tonnage while boosting stiffness. - Enhance O&M Efficiency
• Implement digital twins and AI predictive maintenance to shift from break-fix to plan-fix, reducing downtime by ~30 %.
• Employ autonomous drones and ROVs for routine inspections, cutting crew and vessel costs by 20–25 %. - Optimize Supply Chain
• Cluster fabrication at domestic shipyards to cut transport and currency risks.
• Diversify turbine and cable suppliers to secure competitive pricing and reduce lead-time exposure. - Leverage Finance & Policy Support
• Maximize grants from NEDO and regional revitalization funds for feasibility, demonstration, and EIA costs.
• Tap green bonds and ESG-linked loans to lower financing costs by 1–2 percentage points.
• Pool early-phase risks via government guarantees or industry insurance schemes.
By combining scale-up, innovation, operational excellence, and strategic finance, floating offshore wind LCOE can be driven from today’s range of ¥12–18/kWh toward—or even below—¥10/kWh. In Part 5, we will examine real-world demonstration and commercial projects to extract lessons learned and further refine cost models.
Conclusion & What’s Next
This case study demonstrates an achievable LCOE of around €135/MWh. With further scale-up and technology maturation, the cost could fall even further. In Part 4, we will explore Japan’s regulatory framework, certification processes, and on-site challenges through real project examples. Stay tuned!
Want to dive deeper? Check out key categories on DeepWind:
🔍 Market Insights – Stay ahead with insights into the latest developments shaping renewable energy investments.
🏛 Policy & Regulation – From auction schemes to FIP reform, get a clear understanding of Japan’s evolving energy rules.
🌊 Projects – Discover the progress and behind-the-scenes of offshore wind projects across Japan.
💡 Technology & Innovation – From next-gen turbines to floating foundations, explore the cutting edge of offshore wind tech.